Aug 27 (LNGJ) - Sabine Pass LNG has filed a report with FERC saying the first engineering stage of the liquefaction trains 1 and 2 at its export terminal in Cameron Parish, Louisiana, is 99.4% complete.
Procurement is 99.5% complete, and subcontract and direct hire construction work are 46.6% and 35.6% complete, respectively.