Sempra Infrastructure has opened the FERC pre‑filing process for Port Arthur LNG North, a four‑train, 27 mtpa expansion of its Texas export terminal that could start shipping LNG in late 2034, if approved by the US energy regulator and financing is secured.
The US Court of Appeals has removed a major legal obstacle to Venture Global’s CP2 LNG export terminal in Louisiana, upholding the Federal Energy Regulatory Commission’s (FERC) approval of the $28 billion project and its associated CP Express pipeline.
U.S. regulators have cleared Cheniere Energy to introduce feed gas into the “warm end” of Midscale Train 7 at the Corpus Christi Stage 3 LNG project as part of commissioning activities.
Gulfstream LNG, an US greenfield project, is advancing through FERC’s pre-filing review, while Texas LNG has already moved further along in the regulatory process and is working toward final authorization.
Golden Pass LNG, the QatarEnergy and ExxonMobil joint venture, has received U.S. regulatory approval to begin preliminary commissioning activities on Train 2 – just two days after the company filed its request.
US federal regulators have granted NextDecade another three years to complete the first five trains at its Rio Grande LNG export project, extending the in-service-deadline to November 2031. NextDecade subsequently filed an application for train 6.
US Federal Energy Regulatory Commission (FERC) has waived the mandatory pre-filing requirement for a third phase of Venture Global’s CP2 LNG expansion, signalling regulator’s openness to streamlining brownfield LNG build-outs. CP2 LNG Phase 3 is designed to boost peak liquefaction capacity from 28 mtpa to 35 mtpa.
Cheniere Energy has filed an application to the Federal Energy Regulatory Commission (FERC), seeking approval to build a new 24 mtpa LNG terminal in Texas. The proposed Train could bring capacity at Cheniere’s Corpus Christi plant to 25 mtpa, with the ongoing Stage 3 expansion due completed by the end of 2026.
ExxonMobil indicated the timeline of getting Golden Pass LNG project into full operation could slip into 2026, though commissioning works are already underway.
Commonwealth LNG has been granted a regulatory extension of four years to complete its 9.5 mtpa Louisiana export terminal, with the Federal Energy Regulatory Commission (FERC) approving a new construction deadline of 31 December 2031.