Sengkang LNG advances

Written by  John McKay
Friday, 06 October 2017
Free Read

Oct 6 (LNGJ) - Energy World Corp., the LNG project developer, said its Indonesian Sengkang liquefaction venture was well advanced, with key equipment, including four cold-boxes, compressors and ancillary equipment, already installed on site. “The LNG storage tank has been fully slip-formed and is now subject to fit out,” said the Australian-listed company. “Jetty works have been finalised and loading arms have been installed. The interconnecting pipe work and the installation of the control and instrumentation systems are being completed,” added EWC. “As previously advised, the company will bring these projects into commercial operation in 500,000 tonnes per annum phases when we can conclude the LNG product off-take discussions with Perusahaan Listrik Negara, the state electricity company, who require LNG for power operations in eastern Indonesia,” it explained.