Klaipėda LNG terminal operator KN Energies (KN) has revealed details about the planned allocation of LNG regasification capacities for the 2026 terminal gas year.
KN will offer 4 TWh (four conventional cargoes) of terminal regasification capacity. The invitation and conditions to acquire the capacities are due to be announced in December.
Preliminary cargo delivery windows and regasification periods, are:
Cargo No 1 - Delivery window: 24/25th February, 2026. Regasification period: 1st February/31st March, 2026
Cargo No 2 - Delivery window: 19/20th August, 2026. Regasification period: 1/31st August, 2026
Cargo No 3 - Delivery window: 1/2nd September, 2026. Regasification period: 1st September/31st October, 2026
Cargo No 4 -Delivery window: 22/23rd November, 2026. Regasification period: 1st November/31st December, 2026.