Santos vs Fluor- Court finds in favour of Santos

Written by  Ian Cochran
Monday, 11 August 2025
Free Read

Last Friday, Australia’s Queensland Supreme Court ruled in favour of energy developer Santos in proceedings brought by the company against construction company, Fluor Australia.

The Court confirmed that Fluor must pay around A$692 mill to Santos and its co-venturers, with further sums yet to be determined.

This case centred around an engineering and construction contract that Santos signed with Fluor in 2011 for the development of production facilities that formed part of the Gladstone LNG project.

Construction took place between 2011 and 2014.

Santos argued that Fluor was not entitled to all the costs it had claimed and received payment for under the contract and sought to recover those amounts and also made claims to recover liquidated damages associated with the late completion of the project.

In addition, Santos sought to enforce against a parent company guarantee from Fluor Corp.

The Court referred Santos’ claims to three referees who provided their final report on 14th July, 2023. In the referees’ opinion Santos was entitled to recover certain costs.

It upheld the majority of the referees’ findings, affirming that Fluor must pay at least A$692 mill to Santos and its co-venturers, with further sums owing, and the final amount ordered in Santos’ favour (with interest plus legal costs) to be determined in the coming weeks.