Cove Point LNG progress

Written by  John McKay
Friday, 17 February 2017
Free Read

Feb 17 (LNGJ) - The US Cove Point LNG export project in Maryland, owned by Dominion Energy, is almost 75 percent complete, according to the latest progress report filed with the Federal Energy Regulatory Commission. The existing import terminal on Chesapeake Bay is being transformed into a liquefaction plant and is scheduled to come on stream in 2018. “At the terminal, work continued on modifications to the existing plant in the areas of the jetty platforms and tie-in scope,” said Dominion. “Construction activities conducted during the January period included preliminary commissioning activities for new compressor units and associated equipment, final building completion activities, and earthwork for corrosion protection and electrical grounding,” it added.

Rate this item
(0 votes)

Related Video

Free Read