FLNG stays on track

Written by  John McKay
Tuesday, 09 May 2023
Free Read

May 9 (LNGJ) - Kosmos Energy, the developer with UK major BP of the Mauritania and Senegal floating LNG project and natural gas hub, said phase one of the venture called the Greater Tortue Ahmeyim project continued to make good progress. “First gas is targeted at the end of 2023 with continued progress across the four major work streams,” said Dallas, Texas-based Kosmos.

   “Hub construction work is complete and activity is focused on progressing the final commissioning for handover to operations around the end of the second quarter of 2023,” Kosmos explained. “The laying of the deepwater section of the pipeline from the field to the FPSO is currently underway. This will be followed by the installation of the infield flowlines and subsea structures. Timely execution of this subsea work scope is the critical path to first gas by the end of the year,” stated Kosmos.

Last modified on Tuesday, 09 May 2023 10:05
Rate this item
(0 votes)

Related Video

Free Read