July 13 (LNGJ) - Pipeline natural gas flows from Norway to the UK and the European Union were reduced on July 13 after problems at Equinor’s Sleipner gas field cut flow levels to the UK and Belgium. Data from Norwegian pipeline and terminals operator Gassco showed that Norwegian aggregated exit (nomination) flows on July 13, including UK Easington and Zeebrugge in Belgium, were at 256.6 million cubic metres. The flows to Belgium were at 23.9 mcm, about 50 percent below normal, and the Easington flows were also down at 10.4 mcm.