Golar and bp settle their differences

Tuesday, 06 August 2024
Free Read

Golar LNG and bp, as operator of the Mauretania/Senegal Greater Tortue-Ahmeyim LNG project, have signed agreements to implement a commercial reset for the FLNG ’Gimi’. 

This commercial reset agreement simplifies contractual cash flows and settles previous disputes related to payment mechanisms for pre-commercial operations date (pre-COD) contractual cash flows. 

Golar and bp have agreed an updated schedule of daily payments until the commercial operations date (COD), which have step-up mechanisms based on project milestones up to COD and are secured by long stop dates. 

Golar will also be entitled to certain lump sum bonus payments subject to achievement of certain project milestones. 

These pre-COD cash flows are expected to be deferred on the balance sheet and amortised over the 20-year contract term from COD.

This commercial reset settles all ongoing disputes, including the current arbitration process and re-aligns the parties towards reaching COD, Golar said.

To shorten the time to COD, the parties have also agreed to start the commissioning of FLNG ’Gimi’ with an LNG cargo prior to the availability of gas from the FPSO. 

Last modified on Wednesday, 07 August 2024 10:38