Reliance Industries of India and BP of the UK said a second natural gas field had come on stream ahead of the mid-2021 schedule in the Krishna Godavari Basin offshore the Indian East Coast, adding to the nation’s gas supply in addition to LNG shipments.
McDermott International, the US energy and LNG engineering company, said that first gas had flowed from a field development of India's Oil and Natural Gas Corp. (ONGC) in the offshore Krishna Godavari Basin in the Bay of Bengal.
McDermott was awarded the offshore contract for ONGC’s 98/2 Block in the KG Basin in October 2018.
The KG 98/2 block is situated offshore the Godavari River delta, about 35 kilometres off the East Coast state of Andhra Pradesh and extends for 7,290 square kilometres in water depths ranging from 300 metres to 3,200 metres.
It is currently one of the largest subsea projects in India and included the supply of a package including production systems (SPS), including 26 deepwater trees, and the installation of subsea umbilicals, risers and flowlines.
The early first gas involved the tie-back of a single well to the existing Vashishta facility.
At 4,265 feet (1,300 metres), the first well that has been opened for early first gas is the deepest water depth opened by ONGC.
The ONGC gas field will further help satisfy India's growing natural gas demand, about half of which is made up of domestic pipeline gas supplies from areas like the KG Basin, wile the other half comes from LNG imports.
“McDermott is a leader in the subsea space and we have worked incredibly hard to fast-track the production to early first gas,” said Ian Prescott, McDermott's Senior Vice President for Asia Pacific.
“To deliver this accelerated schedule is an exceptional achievement and testament to the benefits of the collaborative commercial model put forward to ONGC,” Prescott explained.
“Production from a deepwater well in less than 14 months is an outstanding achievement for the exploration and production industry,” he stated.
McDermott said that in line with the “Made in India' approach for the 98/2 project, a substantial amount of engineering and project management has been led from McDermott's operations in Chennai.
“This local approach is a new initiative in the deepwater subsea space for McDermott,” said the Houston-based company.
“We look forward to continuing our work in the Bay of Bengal as we help ONGC meet India's growing energy demands,” it added.
McDermott has been conducting business as usual while having to ease its financial concerns in mid-March when a US bankruptcy court in Texas approved the sale of its Lummus Technology business to global equity funds.
Under the terms of the Chapter 11 plan, McDermott will complete a comprehensive restructuring forced on it by financial problems, including those that arose from takeover of CB&I.
McDermott is involved in some of the world’s leading LNG construction projects, including several on the US Gulf Coast and the North Field Expansion in Qatar.
Currently McDermott is working with other firms on both the Cameron LNG project at Hackberry in Louisiana and the Freeport export facility at Quintana Island in Texas.
McDermott has additionally been engaged as a contractor on the Golden Pass LNG export project for Qatar Petroleum and ExxonMobil venture in Texas.