Delfin LNG, the US floating liquefaction and export project proposed for offshore Louisiana, has filed with the Federal Energy Regulatory Commission for a third extension of permits to complete the venture.
The Cheniere Energy-owned Corpus Christi LNG export plant in Texas is the first of the four US Gulf Coast-based facilities to recommence cargo liftings since activities were temporarily halted as Hurricane Laura approached last week, while seven LNG carriers are standing by in the Gulf to load.
The Corpus Christi plant began loading cargoes again just two days after the hurricane made landfall farther north in the Gulf of Mexico near Lake Charles on the Louisiana-Texas border.
The first cargo was loaded on August 30 onto the 177,200 cubic metres capacity “Sohshu Maru”, with another cargo being taken by the 140,645 cubic metres capacity “Golar Arctic” and a third on August 31 by the 155,000 cubic metres capacity “Gaslog Shanghai”, according to shipping data.
Renewed cargo liftings helped to boost Gulf Coast LNG cargo futures to their highest levels in 2020. These are settled derivatives contracts available through to October 2022 and based on the average free-on-board (FOB) cargo prices.
The value of a US GCL cargo for October 2020 rose to $3.600, up from $3.250 per MMBtu on August 31, while November jumped to $4.486 from $4.347 per MMBtu.
The December GCL contract increased to $4.973 per MMBtu from $4.905 per MMBtu on August 31.
Before the Corpus Christi plant began cargo liftings the last cargo loaded in the GoM had been on August 23, the shipping data showed.
There were also seven unladen LNG carriers on September 2 either in a holding pattern offshore or entering the Gulf.
Other plants were also on the way back. Cheniere said that a comprehensive facility and operational assessment of its Sabine Pass plant in Louisiana, the largest facility in the US with 22.5 MTPA of nameplate capacity, had revealed no significant damage as a result of the hurricane.
“Cheniere has started to execute on its plan to restart LNG production at Sabine Pass,” said the company.
Sempra Energy, the owner of the Cameron LNG export plant in Louisiana, said its teams had been able to conduct preliminary visual inspections of the Cameron facility and the site of the proposed Port Arthur LNG project in Texas and of other infrastructure in the region.
“The initial evaluation indicates minimal flooding and no catastrophic wind damage,” said Sempra.
“Thorough inspections are planned pending confirmation of sufficient site safety and security. The team at Cameron LNG is committed to the restoration of full operations as soon as safely practicable,” added the company.
Venture Global, the Virginia-based company developing three liquefaction and export plants in Louisiana, said its Calcasieu Pass facility under construction in Cameron Parish had sustained minimal impacts from the hurricane, which passed directly over the project site.
“A walk-through inspection of most areas of the site following the storm confirmed that the project site’s robust storm protection system, including a perimeter wall and storm water pumping system, performed as designed,” said Venture Global.
“While we are relieved by the minimal impacts to Calcasieu Pass LNG, we are mindful that the surrounding communities of Cameron and Lake Charles have suffered significant damage from this powerful and historic storm,” the company added.
The cancellation of LNG cargoes from Gulf Coast export plants amid over-supply and a price collapse is set to be offset by an increase in pipeline exports to Mexico, the largest component of US natural gas trade and a key take-away portion of still high production levels.