Pembina Pipeline Corp. and the Haisla First Nation from Kitimat in British Columbia have received environmental approvals to proceed with the near-shore Cedar LNG project on the Douglas Channel and have also signed a feed-gas tolling accord.
Woodfibre LNG, the mid-scale project near the town of Squamish in British Columbia, has issued a notice to proceed to US energy engineering contractor McDermott International.
A third large-scale LNG export joint venture is being considered based on previous projects discussed since 2015 and has been outlined by a First Nation representative at a council meeting in the city of Terrace located near the Skeena River in northern British Columbia.
The Canadian Woodfibre LNG project being developed by the Asia-based Royal Golden Eagle (RGE) group of Indonesian businessman Sukanto Tanoto has pushed back the start of construction until the end of summer 2021.
Woodfibre President David Keane, who is retiring at the end of November but will continue to be an adviser to the project in British Columbia, said the parent company was expected to make a final investment decision by the third quarter of 2021.
“Construction would start shortly thereafter, with the plant expected to be producing liquefied natural gas for export by late 2025,” said Keane.
The outgoing President explained that the delay had been caused by several issues, not least the Covid-19 pandemic.
The project has been affected by Covid-19 temporarily closing LNG-module fabrication yards in Asia. The delay also forced the company to apply for a five-year extension to its provincial environmental certificate.
Before joining the Woodfibre project in 2018, Keane had been the Chief Executive of the industry lobbying group, the BC LNG Alliance, now called the Canadian LNG Alliance, for four years.
Woodfibre LNG is a small-scale venture with plans to export to Asia, where the parent company has offices in Singapore, Jakarta, Hong Kong, Nanjing and Beijing.
The Woodfibre plant is sited on a brownfield site of a former pulp mill, about 7 kilometre from the town of Squamish and 70km northeast of Vancouver.
It was granted a permit back in July 2019 by the provincial authorities to proceed with construction.
The plant when completed will comprise a facility with output of 2.1 million tonnes per annum and LNG and storage tanks with 250,000 cubic metres of capacity. The projected cost is around US$1.4Bln.
Woodfibre had close cooperation in the environmental assessment process with the native North American Squamish First Nation in the area of the proposed plant.
Earlier in November 2020, the BC Environmental Assessment Office also granted utility and infrastructure company FortisBC a five-year extension to its environmental certificate for a new 47-kilometre pipeline that will supply natural gas to the Woodfibre plant.
In the meantime, Woodfibre has been working on the remediation of its site so that it is ready for construction next year.
Canadian political tension over energy and environmental policies and the development of natural gas, LNG exports and minerals are escalating as ministers in three provinces have rejected the approach of the federal government in Ottawa, saying it offered no real solutions to carbon emissions beyond taxing hard-working families and businesses.